Athens Building Corp.is awarded the Construction contract for the New Kent Middle School Addition. The project consists of building additions/alteration of a second floor structure to the existing building. Building of 6 new classrooms as well as the renovations to the existing corridor. The project value is over $1M and the completion schedule is 180 days

7/14/2017 – Work in Progress at the Middle School. The Project is 84 Days ahead of Schedule in an effort to complete the project prior to school starting in the fall.

Project Completed, October 2017