With stunning waterfront vistas and innovative architecture, living in Downtown Norfolk appeals to those who appreciate sensory pleasures. There’s also a touch of historic allure, as older brick buildings have been transformed into charming condos. These luxurious waterfront condominiums provide upscale living along the Elizabeth River. Built on a former city pier, the gated community consists of three distinct buildings. Athens Building Corporation will be undertaking repairs on the exterior building envelope. The project involves removing, disposing of, and replacing specific cladding components.
April 2025
In April, work on Building 305 focused on removing joint sealant, with crews completing initial sections and progressing to subsequent areas on the front side and section 2. Site mobilization and material deliveries took place in mid-April, and throughout the month, work advanced while documenting existing damaged brick, deteriorated mortar joints, and exposed weatherproofing membranes—especially near first-story windows and on the fourth floor—which will require further attention as the project moves forward.
May 2025
Throughout May, work primarily focused on removing and reinstalling joint sealant on Buildings 301, 303, and 305. Early in the month, crews removed thousands of linear feet of old sealant from sides and fronts of the buildings, documenting damaged brick and mortar along the way. After removal, crews began installing new sealant, including white sealant on windows and doors and red sealant on vertical and horizontal expansion joints, totaling hundreds of linear feet each day. Productivity averaged 16–33 linear feet per person per hour depending on crew size and weather conditions.
June 2025
Throughout June, work focused on installing joint sealant on Buildings 301, 303, and 305, including both vertical/horizontal expansion joints and window/door applications. Crews installed hundreds of linear feet of red sealant on expansion joints and white sealant on windows, doors, and balconies, averaging 17–34 linear feet per person per hour depending on crew size and scope. Notable progress included sealing balconies, multiple doors and windows, and large sections of front and side walls. Rain delays and careful removal/replacement of old sealant were accounted for during the month, ensuring proper adhesion and alignment. Overall, June marked significant advancement toward fully sealed, weatherproofed building exteriors.
July 2025
In July, crews continued removing and installing joint sealant on Buildings 301 and 305. Work included installation of roughly 256 ft of white sealant on upper areas of both buildings and approximately 220 ft of red and white sealant on building 301, including balcony and window sections. Additionally, mobilization of a barge and equipment allowed work to progress on the opposite side of building 301, where crews removed about 80 ft of old joint sealant. These activities advanced the weatherproofing and overall exterior sealing of the buildings.